Washington, DC—(ENEWSPF)—June 22, 2011 – Update as of 5 p.m. EDT
Pillars Installed To Support Used Fuel Pool
Plant Status
Tokyo Electric Power Co. workers have installed 32 steel pillarsto support the reactor 4 spent fuel pool at the Fukushima Daiichi nuclear energy facility and improve its capability to withstand earthquakes. The company next will wrap the pillars in concrete. It plans to finish the project by the end of July. The walls supporting…