Washington, D.C.–(ENEWSPF)–March 25, 2011 – UPDATE AS OF 1:30 P.M. EDT.
Workers have switched from sea water to fresh water to cool reactor 1 and were expected to make the same change for reactors 2 and 3 at the Fukushima Daiichi nuclear power plant by Saturday. Pressure and temperature inside reactor 1 were declining on Friday.
Lighting has been restored in the control rooms of reactors 1 through 4 at the plant, which lost electric…